Do You Need a Permit for a Retaining Wall in Kingston?
Retaining walls are one of the projects we build most often around Kingston, and one of the first questions homeowners ask is whether they need a permit. The short answer: most low garden walls do not. But the height of the wall, where it sits and what is around it can change that quickly. Here is what to know before you build.
The 1 Metre Rule in the Ontario Building Code
The Ontario Building Code treats some retaining walls as "designated structures," which means they need a building permit, just like a deck or an addition. A retaining wall falls into that group when it is more than 1,000 mm (about 3.3 feet) in exposed height and sits next to:
- Public property, such as a sidewalk, road or park
- Access to a building, such as a walkway or driveway people use to reach a door
- Private property that the public is allowed onto
Exposed height is the part of the wall you can see above the finished ground at its base. Walls that meet this test also need a design that meets the structural requirements of the Building Code, which in practice usually means drawings from a professional engineer.
A tall wall beside a walkway, patio or driveway may also need a guard, such as a railing, to keep people from falling over the edge.
Why "Next To" Catches More Walls Than You Might Think
Many front yard walls run along the walkway to the front door or beside the driveway. Both count as access to a building. So a 1.2 metre wall holding back a front slope beside your front path is likely to need a permit, while a 60 cm garden wall in the back corner of a fenced yard generally will not.
Municipalities do not always read these rules the same way, and some have added their own. If your wall is close to a metre tall, or close to a sidewalk, path or driveway, it is worth a quick call to the City of Kingston's building department, or your township's, before the design is final.
Two Short Walls Are Not Always a Loophole
Terracing a slope with two or three shorter walls is often a better design than one tall wall. It looks softer, gives you planting beds and spreads out the load. The walls need to be spaced properly, though. Walls stacked too close together behave like one tall wall, and a building official may treat them that way.

Near the Water? You May Need a Second Permit
A building permit is only part of the picture on waterfront and low-lying properties. Cataraqui Conservation regulates work in and near lakes, rivers, wetlands and floodplains across the Kingston area under Ontario Regulation 41/24, and shoreline walls and erosion work usually need their permit. That permit is separate from any building permit.
Along the Rideau Canal, work at or below the water's edge also needs approval from Parks Canada. If you are planning a wall on a lake or river property, find out what applies early, because approvals can take a while. We cover more of this on our Rideau Lakes and Wolfe Island and Howe Island pages.
Call Before You Dig, Every Time
Every retaining wall starts with excavation for the base, so a free utility locate through Ontario One Call comes before any digging. Gas, hydro and communication lines are often closer to the surface than people expect, especially along front yards and driveways.
Property Lines and Your Neighbours
A wall right on the lot line, or one that changes how water flows onto the property next door, can turn into a dispute. Know where your property line is, keep the wall and its drainage on your side, and talk to your neighbour before work starts if the wall will be close to their yard.
No Permit Still Means Building It Properly
Most walls fail because of what is behind and under them, not the blocks themselves. A compacted base, drainage stone and a drain pipe behind the wall, and reinforcement on taller block walls all matter, permit or no permit. Our post on why it is not always the wall that fails goes into more detail, and our complete guide to retaining walls in Kingston covers design, cost and care.
How We Handle Permits on Wall Projects
On every retaining wall project, we look at height, location and what is around the wall during the first site visit. If a wall needs a permit, an engineered design or a conservation authority approval, we tell you up front and build it into the plan and the timeline, so there are no surprises halfway through.
Rules change and every property is different, so always confirm the requirements with your local building department before you build.
Planning a wall for next spring? Winter is a good time to sort out design and approvals so you are ready when the ground thaws. Book a site visit and we will walk through it with you.